Jama Connect User Guide

Change a project key

Note

You must have project or organization administrator permissions to change a project key.

  1. In the project whose key you want to modify, open the Configure project window and view the current project key. (If you are an organization administrator you can also select Admin > Manage all projects, and then choose the project you want to modify.)

  2. Select Change project key in the upper right corner of the window to open the Confirm project key change window.

  3. Enter the new project key. Note that keys must be 1-16 characters long , consisting of letters, numbers and underscores.

  4. Select Submit. Once the project key has been updated, the Unique ID of all items within that project will be updated to contain the new key.