Replace current items with a baselined version
When you replace current items with a baselined version, a new version of the item is created and content is replaced with the baseline content. No versions are lost.
Important considerations
Items that were deleted are restored to the version when the baseline was created.
Relationships that were deleted aren't restored.
You can restore a prior version of an individual item from the versions tab in Single Item View.
Note
You must have project or organization admin permissions to do this.
To replace current items with a baselined version:
Select the baseline you want to revert to in the Baselines tab of the Explorer Tree.
Select Replace with baseline.
In the confirmation message, select Replace.
A pop-up message displays the number of items that were updated.